The complete UNI 60 project in eleven ordered stages — from unpacking the crate to the first heating season, with links to the detailed page for each step.

Updated

A UNI 60 installation runs in eleven stages, and skipping any of the first eight will cost you later. Use this page as the project checklist; each step links to the page that covers it in full.

First firing is not a DIY step

Section 6.4 of the UNI boiler manual requires the first firings to be carried out by a trained installer or service technician. Electrical connections must be made by a qualified electrician.

Confirm the boiler suits the building

Check the heat load against the UNI 60's 85–205 KBTU output and 5,000 ft² nominal coverage. Square-footage figures are approximate — real sizing depends on heat loss, insulation and climate.

Specifications

Inspect the delivery

Check the boiler for shipping and mechanical damage before accepting it, and confirm every item on the packing list is present. After sale, the distributor will not accept claims for incompleteness or mechanical damage.

What's in the box

Read the safety rules

Pressure, temperature and fuel limits govern every later decision. Maximum operating pressure is 15 psi, maximum flow temperature 185 °F, and the boiler must never run without a relief valve.

Safety

Lay out the boiler room

Set the clearances, the floor, and the service access before anything is moved into place. You need 36 in at the front to clean the boiler and at least 24 in behind it.

Boiler room and clearances

Size and specify the chimney

The flue must be at least the diameter of the boiler outlet — 8 in for the UNI 60 — in acid-resistant stainless steel, insulated wherever it is exposed.

Chimney requirements

Design the hydronic system

Closed system, expansion tank, relief valve, return-temperature protection and — in almost every case — a buffer tank.

System design · Buffer tank and hot water

Position and pipe the boiler

Set the boiler level on a non-combustible floor, connect 2 in supply and return, fit the relief valve and drain, and connect the flue.

Positioning · Piping

Fill and pressure-test

Fill with clean water of no more than 2 ppm hardness, vent the system, and test. Maximum test pressure is 50 psi.

Filling and water quality

Wire the controller, sensors and pumps

Boiler sensor into the immersion well, STB clamped to the supply, fan and pumps to their outputs, thermostat to I2. A 120 V pump needs the supplied 230 V relay block.

Electrical and sensors · Pump wiring

Apply the MBtek settings for the UNI 60 before the first fire — the factory defaults are generic and will not burn well in this boiler.

Recommended settings

Fire it, then hand it over

Check the draft, load the firebox, ignite, run Start Fire, and stay with the boiler. Then train the owner on loading, ash removal and the cleaning schedule.

First firing · Maintenance schedule

Settings cheat sheet

These are the MBtek-recommended UNI 60 values — set them at commissioning. Full explanations are on the recommended settings page.

SettingValue
Boiler setpoint65 °C / 149 °F
Exhaust setpoint160–240 °C / 320–464 °F
Maximum fan speed80 %
Minimum fan speed40 %
Fan performance in supervision35 %
Fan ON (purge) time10 s
Fan OFF (pause) time5 min
Fan typeWPA 07 / DM85
Boiler hysteresis2 °C / 5 °F
Fan slowdown threshold12 °C / 21 °F
Maximum boiler temperature80 °C / 176 °F
Boiler shutdown temperature35 °C / 95 °F
Pump start temperature35 °C / 95 °F
Boiler cooling temperature78 °C / 172 °F
Firing-up time120 min
Brager Expert exhaust — firing-up time10 min

Want a second pair of eyes on the plan?

MBtek technical support can help with sizing, commissioning and controller settings.

NextHow the UNI 60 works

The combustion path, the three flue passes, and what the fan and controller actually do.

On this page